To: BNSF Intermodal Customers
08/22/2008

Construction at BNSF’s St. Paul Facility Beginning This Weekend

Beginning this Saturday, August 23, and continuing through Friday, September 5, a portion of BNSF’s St. Paul Facility Lot 20 will be under construction. The lot will undergo grading and resurfacing improvements and dust control for a length of 300 feet on the west end of the lot.

The in- and outgates will operate as usual, but drivers may experience slower gate times during these dates.

Also, heavy traffic in the area for construction and yard improvements will cause additional delays at the gates and on Arundel St. during the following times:
Monday, September 1 – 2:00 p.m.-5:00 p.m. and 6:00 p.m.-10:30 p.m.
Tuesday, September 2, through Thursday, September 4 – 5:30 p.m.-10:30 p.m.

If you have any questions regarding this temporary change, please contact BNSF’s Hub Manager at 651-298-7045.